Road work in Davidson begins today

Town of Davidson

Oct. 24. As part of Davidson’s annual streets resurfacing project, road work is starting Monday Oct. 24, and will last about three weeks. 

This is the second year of a  comprehensive five-year plan to maintain and improve streets throughout Davidson.

The plan focuses paving in tight geographic areas to be the most cost-effective, and will generally move west to east during the five years.

$600,000 of the Town of Davidson budget is allocated each year toward these paving related activities.

As seen in the map, streets that will be worked on are located west of Main Street and largely north of Griffith Street. The expected completion date is Tuesday, Nov. 15, 2022.

There will be temporary lane closures while the work is done, but no road closures are expected.